HOME / OUTAGES / NEWLANDS AND NGAURANGA

Newlands and Ngauranga

#2268487
Unplanned outage
Restored

There's a power cut in this area. Thanks for bearing with us – we'll keep you updated right here.
What to do in a power outage

Latest update

Customers affected

146

Start date/time

31/07/2024 05:27pm

End date/time

1/08/2024 01:18am

Network outage - line/cable fault. Power has been fully restored

Last updated 1/08/2024 01:18am

Previous updates

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

1/08/2024 02:00am

Network outage - line/cable fault. We are working to restore power as quickly and as safely as possible

Last updated 1/08/2024 12:52am

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

1/08/2024 01:00am

Network outage - line/cable fault. We are working to restore power as quickly and as safely as possible

Last updated 1/08/2024 12:29am

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

1/08/2024 01:00am

Network outage - line/cable fault. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 11:58pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:59pm

Network outage - line/cable fault. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 11:34pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:59pm

Network outage - line/cable fault. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 11:00pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:30pm

Network outage - line/cable fault. Power has been partially restored. We are working to restore full power as quickly and as safely as possible

Last updated 31/07/2024 10:36pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:30pm

Network outage - line/cable fault. Power has been partially restored. We are working to restore full power as quickly and as safely as possible

Last updated 31/07/2024 10:04pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:30pm

Network outage - line/cable fault. Power has been partially restored. We are working to restore full power as quickly and as safely as possible

Last updated 31/07/2024 09:31pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:30pm

Network outage - line/cable fault. Power has been partially restored. We are working to restore full power as quickly and as safely as possible

Last updated 31/07/2024 09:00pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:30pm

Network outage - cause to be determined. Power has been partially restored. We are working to restore full power as quickly and as safely as possible

Last updated 31/07/2024 08:30pm

Customers affected

146

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 11:30pm

Network outage - cause to be determined. Power has been partially restored. We are working to restore full power as quickly and as safely as possible

Last updated 31/07/2024 08:27pm

Customers affected

1127

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 08:30pm

Network outage - cause to be determined. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 08:02pm

Customers affected

1127

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 08:30pm

Network outage - cause to be determined. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 07:43pm

Customers affected

Yet to be advised, fault crew attending

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 08:30pm

Local area outage - cause to be determined. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 07:38pm

Customers affected

Yet to be advised, fault crew attending

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 08:30pm

Local area outage - cause to be determined. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 07:07pm

Customers affected

Yet to be advised, fault crew attending

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 08:30pm

Local area outage - cause to be determined. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 06:29pm

Customers affected

Yet to be advised, fault crew attending

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 08:30pm

Local area outage - cause to be determined. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 05:58pm

Customers affected

Yet to be advised, fault crew attending

Start date/time

31/07/2024 05:27pm

Estimated restoration

31/07/2024 08:30pm

Local area outage - cause to be determined. We are working to restore power as quickly and as safely as possible

Last updated 31/07/2024 05:27pm

Streets affected

  • Boeing Way, Newlands
  • Centennial Highway, Ngauranga
  • Epic Way, Newlands
  • Grumman Lane, Newlands
  • Newlands Road, Newlands
  • Piper Way, Newlands
  • Spenmoor Street, Newlands
  • Wakely Road, Newlands